Client story

Refurbishment of Boralex premisses in Lille

Size

500 sqm

Duration

2 months

Approx.

30 workplaces

Challenge

The client's challenge was to bring together all of its employees on a single platform in order to optimise the synergy between departments. It was also a question of working on the comfort of the work spaces, i.e. improving the overall acoustics and providing natural light. The project is part of a circular economy approach, with the reuse and recovery of furniture and partitioning.

Solution

The fitting out work carried out enabled us to meet these needs within 2 months while respecting the client's graphic charter. We renovated the floor and wall coverings, made the partitions, selected and installed custom-made furniture and installed decorative lighting. décoratif.

We'd love to hear from you

Get in Touch